Subject: 9.2 Newkirk Novak Construction Partners - Transfer of Funds - PCHS Rebuild (Phase One) Project
Comprehensive School Improvement Plan:
2021 - 2022 Goal A-1 Academics
Develop and enhance quality educational/instructional programs to improve overall and individual student academic performance.
2021 - 2022 Goal B-1 Business
Proactively and responsibly manage district growth, finances, and support services to improve student achievement.
2021 - 2022 Goal C-1 Community/Students
Provide each student with a relevant education in a safe and caring environment.
2021 - 2022 Goal C-2 Community/Staff
Attract, retain, and develop a high quality staff.
2021 - 2022 Goal C-3 Community/Parents & Members
Improve internal and external stakeholder communication, involvement, and partnership.
Policy: DA - FISCAL RESPONSIBILITY
Enclosure Newkirk Novak Construction Partners - Transfer of Funds Memo (6/8/22) - PCHS Rebuild (Phase One) Project
File Attachment:
Newkirk Novak Transfer of Funds Memo 06082022.pdf
Summary: The PCHS Rebuild (Phase One) Project total budget is $57,100,696. The total project budget includes soft costs (owner costs) and hard costs (construction cost) as shown on the attached memorandum.

We are proposing to transfer $284,000 of the soft costs to hard construction costs. This transfer does not change the overall project budget.
Funding:
Recommendation: It is recommended the Board of Education approve the transfer of funds from unused soft costs to hard costs in the amount of $284,000 for the PCHS Rebuild (Phase One) Project as proposed by Newkirk Novak Construction Partners (6/8/22) as submitted.
Approvals:
Recommended By:
Signed By:
Vicki Diggs - Secretary to the Board of Education
Signed By:
Dr. Jay Harris - Executive Director of Operations
Vote Results:

Original Motion
Member Bobby Vann Moved, Member Sharon Sherwood seconded to approve the Original motion 'It is recommended the Board of Education approve the transfer of funds from unused soft costs to hard costs in the amount of $284,000 for the PCHS Rebuild (Phase One) Project as proposed by Newkirk Novak Construction Partners (6/8/22) as submitted.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 7 Nay: 0.
The motion Carried 7 - 0
   
Sharon Sherwood     Yes
Buffy Smith     Yes
Doug Doll     Yes
Bobby Vann     Yes
Karen Bryant     Yes
Shawn Chiddix     Yes
Mike Matousek     Yes