Subject: 5.13 Furniture Order #1B Quotation (232069) - Scott Rice Office Works - PCHS Rebuild (Phase One)
Comprehensive School Improvement Plan:
2021 - 2022 Goal B-1 Business
Proactively and responsibly manage district growth, finances, and support services to improve student achievement.
Policy: DA - FISCAL RESPONSIBILITY
Enclosure Furniture Order #1B Quotation (232069) from Scott Rice Office Works 06092022; Furniture Order #1B Quotation (232069) Acceptance Agreement from Scott Rice Office Works 06092022
File Attachment:
PCHS Rebuild Furniture Quotation #1B June 2022.PDF
20220609 - Platte County HS - Phase 1B - Acceptance Agreement 232069.pdf
Summary: Quotation #1 for furniture for the PCHS Rebuild (Phase 1) project was board approved at the April 21, 2022 board meeting. The attached quotation (#1B) is provided for consideration by the members of the Board of Education. Quotation #1B includes classroom furniture, markerboards, and tackboards, including installation.

Both furniture quotations (#1 and #1B) were procured by advertising bid requests from furniture vendors utilizing furniture and equipment layouts from the design team. Furniture vendors were requested to provide bids on the furniture design layouts using their recommended products based on pricing from a cooperative purchasing program. Three furniture vendors provided bids, and Scott Rice Office Works submitted the lowest quotations (both #1 and #1B) based on design specifications. Quotations were accepted from the following vendors:

Freedom Interiors
Scott Rice Office Works
SSI Furnishings

Quotations #1 and #1B complete approximately 95% of the total furniture designed for PCHS Rebuild (Phase 1) project. These quotations are within the furniture budget planned for the project.
Funding:
Recommendation: It is recommended the Board of Education approve the furniture order #1B quotation (232069) and the acceptance agreement for the PCHS Rebuild (Phase One) in the amount of $359,879.69 from Scott Rice Office Works as submitted.
Approvals:
Recommended By:
Signed By:
Vicki Diggs - Secretary to the Board of Education
Signed By:
Dr. Jay Harris - Executive Director of Operations
Vote Results:

Original Motion
Member Bobby Vann Moved, Member Sharon Sherwood seconded to approve the Original motion 'It is recommended the Board of Education approve the furniture order #1B quotation (232069) and the acceptance agreement for the PCHS Rebuild (Phase One) in the amount of $359,879.69 from Scott Rice Office Works as submitted.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 7 Nay: 0.
The motion Carried 7 - 0
   
Sharon Sherwood     Yes
Buffy Smith     Yes
Doug Doll     Yes
Bobby Vann     Yes
Karen Bryant     Yes
Shawn Chiddix     Yes
Mike Matousek     Yes